The original Loadquip ProLift was a robust, one-of-a-kind machine, custom-designed by our mechanical engineering consulting arm, CMP Engineers, for safely removing and installing chutes on train loadout (TLO) systems at iron ore mines. Built to standard 20′ container dimensions for easy transport, it works with a customised frame and features adjustable platform movements to precisely align chute flanges. Powered by a diesel engine with hydraulically controlled motions, it is operated via a custom wireless remote control linked to a Programmable Logic Controller (PLC), which manages speed, positioning, pressure limits, and provides diagnostic reporting. By reducing manual handling, the ProLift significantly improves the safety and efficiency of chute change-outs.
In mid-2025, the first ProLift machine underwent a full inspection and rebuild after approximately nine years in service, with the bulk of the physical work conducted by Fluid Precision at their premises in Deception Bay. Included in the project scope was a full disassembly and inspection, non-destructive testing (NDT); minor modification of the structure to bring the machine in line with the ProLift II (produced in 2019); design, supply and installation of new guards for hydraulic cylinders and key mechanisms; and finally, re-assembly with new or refurbished componentry and completion of comprehensive static and dynamic commissioning tests.
Thanks to Diamondblast Sandblasting and Protective Coatings, the machine was also given an updated colour scheme in association with Sandvik’s new branding. The ProLift machines were originally designed for Schenck Process, which was subsequently acquired by Sandvik in 2022.
Another aspect of the project involved upgrading the remote monitoring and support system. In collaboration with Noddy Electrical, Loadquip and CMP Engineers successfully upgraded the associated hardware and control system programming to enable improved functionality.
The condition of the almost decade-old ProLift machine was found to be excellent, following thorough NDT conducted by AMAP Engineering that did not pick up any structural defects, and damage to other auxiliary components was typical of general wear and tear. Commissioning of the ProLift was completed efficiently with functionality safely verified at the machine’s working load limit (WLL). The refurbished ProLift machine was returned to Sandvik’s premises in Perth on the 30th of July 2025, ahead of the project deadline.
The Loadquip ProLift upgrade project outcomes will guide maintenance and overhaul scheduling for all ProLift machines in future. The new and improved design features will also transform machine usability and longevity in the subsequent life period.

Custom engineering that’s built to last
Since 1995, Loadquip has been a trusted industry OEM, delivering engineered solutions to the mining and heavy industry sectors. As the manufacturing arm of CMP Engineers, we take pride in designing and manufacturing specialised heavy mining equipment, including low loaders, tow links, magnetic sweepers, and specialised lifting equipment, such as the ProLift, all built to handle the toughest conditions.
Do you need help designing a unique, complex, custom piece of machinery that currently doesn’t exist? Look no further than our team of mechanical and mechatronics engineers who are uniquely positioned to deliver you a bespoke solution in heavy industry.
Contact Loadquip today via +61 7 3839 2045 or email@loadquip.com.au, or visit loadquip.ironbarkmarketing.com/ for more information
Or to discover more about Sandvik’s train loadout (TLO) systems, visit: https://www.rockprocessing.sandvik/en/products/train-loaders